Control de insumos, personal y avance de obra para el proyecto "Rehabilitación del puente sobre el Río Sarapiquí" Puerto Viejo de Sarapiquí, Ruta Nacional # 4
Resumen
This report contains the results of the creation of
a cost control tool developed by Microsoft Access
®, the results that are possible to obtain by
making use of it and a brief description of the use
and handling of the tool are presented.
The tool is used in the bridge
rehabilitation project on the Sarapiquí River,
National Route # 4 consists of an intervention of
sub and super structure, however the activities
discussed are reinforcing steel, the project
creating access and conditioning and protection
of a slope.
The developed tool allows the engineer in
charge of the project in different fields of
construction meet the actual cost of the activities
carried out, the material still has, among others,
so you can take decisions that are required on the
course of the project.
The use of the tool for future projects
allows the engineer to know indirectly yields,
costs and project delivery times, so also will allow
you foresee them in the best way in upcoming
projects.
Descripción
Proyecto de Graduación (Licenciatura en Ingeniería en Construcción) Instituto Tecnológico de Costa Rica, Escuela de Ingeniería en Construcción, 2015.