Tecnológico de Costa Rica
  • How to publish in Repositorio TEC?
  • Policies
  • Educational Resources
  • Contact us
    • español
    • English
  • English 
    • español
    • English
  • Login
View Item 
  •   Repository Home
  • Trabajos de Graduación
  • Biblioteca José Figueres Ferrer
  • Escuela de Ingeniería en Construcción
  • Licenciatura en Ingeniería en Construcción
  • View Item
  •   Repository Home
  • Trabajos de Graduación
  • Biblioteca José Figueres Ferrer
  • Escuela de Ingeniería en Construcción
  • Licenciatura en Ingeniería en Construcción
  • View Item
JavaScript is disabled for your browser. Some features of this site may not work without it.

Browse

All RepositoryCommunities & CollectionsBy Issue DateAuthorsTitlesKeywordEducational Resource TypeIntended UserThis CollectionBy Issue DateAuthorsTitlesKeywordEducational Resource TypeIntended User

My Account

LoginRegister

Statistics

View Usage Statistics

Factores que afectan la construcción de alcantarillado sanitario para la Constructora Fernández Vaglio S.A.

Thumbnail
View/Open
factores_afectan_construccion_alcantarillado_sanitario_para_constructora_fernandez.pdf (1.740Mb)
Date
2018
Author
Coto-Chinchilla, Luis Roberto
Metadata
Show full item record
Abstract
The work presented below is based on the determination of factors that affect the construction of a sanitary pipeline project, to propose tools and methods to be able to reduce the elements identified to the maximum. To locate the factors to be corrected, a control sheet was implemented, which was filled daily by the construction masters and in this way the affectations that occurred were recorded. Once the most frequent factors are known, proposals for improvement are made under the Lean Construction philosophy, which seeks to work more efficiently and use only the resources that are completely necessary. The data shows that there are activities that are not being worked in the right way, which is why they are generating cost overruns and arrears. In addition, with the review of the schedule and the cash flows it is visualized as there is a delay in production, so corrective measures must be taken. At the end of the project, it is determined that to improve the processes there must be field inspection by the project engineers to know if the work is being carried out properly. Also, that a planning that integrates all the work team is a useful methodology for the development of projects
Description
Proyecto de Graduación (Licenciatura en Ingeniería en Construcción) Instituto Tecnológico de Costa Rica, Escuela de Ingeniería en Construcción, 2018.
URI
https://hdl.handle.net/2238/10046
Share
       
Metrics
Collections
  • Licenciatura en Ingeniería en Construcción [553]

|Contact us

Repositorio Institucional del Tecnológico de Costa Rica

Sistema de Bibliotecas del TEC | SIBITEC

© DERECHOS RESERVADOS. Un sitio soportado por DSpace(v. 6.3)

RT-1

 

 


|Contact us

Repositorio Institucional del Tecnológico de Costa Rica

Sistema de Bibliotecas del TEC | SIBITEC

© DERECHOS RESERVADOS. Un sitio soportado por DSpace(v. 6.3)

RT-1