Tecnológico de Costa Rica
  • ¿Cómo publicar en el Repositorio TEC?
  • Políticas
  • Recursos Educativos
  • Contáctenos
    • español
    • English
  • español 
    • español
    • English
  • Login
Ver ítem 
  •   Página Principal
  • Trabajos de Graduación
  • Biblioteca José Figueres Ferrer
  • Escuela de Ingeniería en Construcción
  • Licenciatura en Ingeniería en Construcción
  • Ver ítem
  •   Página Principal
  • Trabajos de Graduación
  • Biblioteca José Figueres Ferrer
  • Escuela de Ingeniería en Construcción
  • Licenciatura en Ingeniería en Construcción
  • Ver ítem
JavaScript is disabled for your browser. Some features of this site may not work without it.

Listar

Todo el RepositorioComunidades & ColeccionesPor fecha de publicaciónAutoresTítulosPalabras clavesTipo de Recurso EducativoDestinatarioEsta colecciónPor fecha de publicaciónAutoresTítulosPalabras clavesTipo de Recurso EducativoDestinatario

Mi cuenta

AccederRegistro

Estadísticas

Ver Estadísticas de uso

Implementación de la metodología de planificación y control “Last Planner” en el proyecto de construcción: Unidad Productiva San Rafael

Thumbnail
Ver/
Implementacion_metodologia_planificacion_control_last_planner.pdf (3.548Mb)
Fecha
2017
Autor
Rodríguez-Porras, Katherine
Metadatos
Mostrar el registro completo del ítem
Resumen
The main purpose of this project is to implement a planning and control system to improve the fulfillment of the activities that constitute a construction project for a period of 10 weeks. The Last Planner System (LPS) utilize Lean Construction philosophy, whose main objective is based in the obtaining of improvements of issues of great importance in the development of a work(productivity, quality, deadlines, among others) The technique consist in generate three types ofprograms, starting from a General Program, breaking it down to conform the Intermediate Program, stage that studies exposed restrictions. Finally, a Weekly Program (directly related to the person in charge of the project) that includes tasks according to the executable activities.Through meetings weekly elaborated were executed results surveys in order to quantify their behavior, evidencing the real progress through graphics, investigating the causes of noncompliance and implementing a culture of continuous improvement. The PPC (Percentage of Promises Completed) stablished a significant increase (from 43% to 63%) from the third week of study, finishing with an 83% on the tenth week. These improvements in compliance are products of a planning that is being constantly verified, taking into account the errors caused and promoting a commitment of all the staff of the project.
Descripción
Proyecto de Graduación (Licenciatura en Ingeniería en Construcción) Instituto Tecnológico de Costa Rica. Escuela de Ingeniería en Construcción, 2017.
URI
https://hdl.handle.net/2238/7296
Compartir
       
Métricas
Colecciones
  • Licenciatura en Ingeniería en Construcción [551]

|Contáctenos

Repositorio Institucional del Tecnológico de Costa Rica

Sistema de Bibliotecas del TEC | SIBITEC

© DERECHOS RESERVADOS. Un sitio soportado por DSpace(v. 6.3)

RT-1

 

 


|Contáctenos

Repositorio Institucional del Tecnológico de Costa Rica

Sistema de Bibliotecas del TEC | SIBITEC

© DERECHOS RESERVADOS. Un sitio soportado por DSpace(v. 6.3)

RT-1