Tecnológico de Costa Rica
  • How to publish in Repositorio TEC?
  • Policies
  • Educational Resources
  • Contact us
    • español
    • English
  • English 
    • español
    • English
  • Login
View Item 
  •   Repository Home
  • Trabajos de Graduación
  • Biblioteca José Figueres Ferrer
  • Escuela de Ingeniería en Construcción
  • Licenciatura en Ingeniería en Construcción
  • View Item
  •   Repository Home
  • Trabajos de Graduación
  • Biblioteca José Figueres Ferrer
  • Escuela de Ingeniería en Construcción
  • Licenciatura en Ingeniería en Construcción
  • View Item
JavaScript is disabled for your browser. Some features of this site may not work without it.

Browse

All RepositoryCommunities & CollectionsBy Issue DateAuthorsTitlesKeywordEducational Resource TypeIntended UserThis CollectionBy Issue DateAuthorsTitlesKeywordEducational Resource TypeIntended User

My Account

LoginRegister

Statistics

View Usage Statistics

Implementación de la metodología de planificación y control “Last Planner” en el proyecto de construcción: Unidad Productiva San Rafael

Thumbnail
View/Open
Implementacion_metodologia_planificacion_control_last_planner.pdf (3.548Mb)
Date
2017
Author
Rodríguez-Porras, Katherine
Metadata
Show full item record
Abstract
The main purpose of this project is to implement a planning and control system to improve the fulfillment of the activities that constitute a construction project for a period of 10 weeks. The Last Planner System (LPS) utilize Lean Construction philosophy, whose main objective is based in the obtaining of improvements of issues of great importance in the development of a work(productivity, quality, deadlines, among others) The technique consist in generate three types ofprograms, starting from a General Program, breaking it down to conform the Intermediate Program, stage that studies exposed restrictions. Finally, a Weekly Program (directly related to the person in charge of the project) that includes tasks according to the executable activities.Through meetings weekly elaborated were executed results surveys in order to quantify their behavior, evidencing the real progress through graphics, investigating the causes of noncompliance and implementing a culture of continuous improvement. The PPC (Percentage of Promises Completed) stablished a significant increase (from 43% to 63%) from the third week of study, finishing with an 83% on the tenth week. These improvements in compliance are products of a planning that is being constantly verified, taking into account the errors caused and promoting a commitment of all the staff of the project.
Description
Proyecto de Graduación (Licenciatura en Ingeniería en Construcción) Instituto Tecnológico de Costa Rica. Escuela de Ingeniería en Construcción, 2017.
URI
https://hdl.handle.net/2238/7296
Share
       
Metrics
Collections
  • Licenciatura en Ingeniería en Construcción [553]

|Contact us

Repositorio Institucional del Tecnológico de Costa Rica

Sistema de Bibliotecas del TEC | SIBITEC

© DERECHOS RESERVADOS. Un sitio soportado por DSpace(v. 6.3)

RT-1

 

 


|Contact us

Repositorio Institucional del Tecnológico de Costa Rica

Sistema de Bibliotecas del TEC | SIBITEC

© DERECHOS RESERVADOS. Un sitio soportado por DSpace(v. 6.3)

RT-1