dc.descriptionProyecto de Graduación (Licenciatura en Ingeniería en Construcción) Instituto Tecnológico de Costa Rica, Escuela de Ingeniería en Construcción, 2019.es
dc.description.abstractLa construcción de pilotes pre excavados en Costa Rica, se ha vuelto una solución muy frecuente en los últimos años, debido a la necesidad de tener cimentaciones profundas en suelos con poca capacidad de soporte, capaces de transmitir grandes cargas al terreno. Este informe se basa en la determinación de rendimientos para el proceso de pilotes pre excavados, el cual se subdividió en tres etapas: perforación, colocación de armadura y de concreto. Adicionalmente se realizó un análisis de productividad mediante tres métodos de medición, work sampling, five minute rating y crew balance, aplicados a los tres subprocesos mencionados anteriormente. También se realizó un análisis de productividad cualitativa al proceso de construcción de pilotes, para determinar causas a nivel global, que afectaban la productividad con un diagrama de Ishikawa. Se obtuvieron rendimientos relacionados a los tres subprocesos de pilotes, así como rendimientos de materiales como el acero y el concreto para 251 pilotes, así como la correlación de los rendimientos de perforación con el perfil geotécnico del proyecto. Finalmente se presenta la productividad que se obtuvo para la construcción de pilotes, lo cual permite tener una referencia de rendimientos y productividad para la construcción de pilotes colados en sitio.es
dc.description.abstractThe construction of pre-excavated piles in Costa Rica has become a very frequent solution in recent years, due to the need to have deep foundations in soils with little support capacity, capable of transmitting large loads to the ground. This report was based on the determination of yields for the pre-excavated pile process, which was subdivided into 3, drilling, reinforcement and concrete placement. Additionally, a quantitative productivity analysis was carried out using 3 methods of productivity measurement, work sampling, five minute rating and crew balance, applied to the 3 subprocesses mentioned above. A qualitative productivity analysis was also carried out on the pile construction process, to determine global causes that affected productivity with a ishikawa diagram. Obtained yields related to the 3 subprocesses of piles, as well as yields of materials such as steel and concrete for 251 piles, as well as the correlation of drilling yields with the geotechnical profile of the project. Finally, the productivity that was obtained for the construction of piles was presented, which allows having a reference of yields and productivity for the construction of piles built on site.es
dc.language.isospaes
dc.publisherInstituto Tecnológico de Costa Ricaes
dc.subjectRendimientoes
dc.subjectProductividades
dc.subjectPiloteses
dc.subjectConcretoes
dc.subjectYieldses
dc.subjectProductivityes
dc.subjectPileses
dc.subjectConcretees
dc.subjectWork samplinges
dc.subjectResearch Subject Categories::TECHNOLOGY::Civil engineering and architecture::Building engineeringes
dc.titleDeterminación de rendimientos y productividad en la construcción de pilotes pre excavados de concreto en el proyecto de Circunvalación Norte (Etapa IV).es
dc.typelicentiateThesises