Análisis comparativo del sistema constructivo de mampostería modular Armabloque con el sistema constructivo de mampostería tradicional
Loading...
Date
Authors
Fuentes-Castillo, Mauricio de Jesús
Journal Title
Journal ISSN
Volume Title
Publisher
Instituto Tecnológico de Costa Rica
Abstract
Este proyecto se basa en el análisis comparativo
del sistema de mampostería modular Armabloque
contra el sistema de mampostería tradicional bajo
el enfoque de costo, plazo, rendimientos de la
mano de obra y calidad. Para ello se evalúan 2
viviendas, la primera desarrollada con el sistema
de mampostería modular Armabloque y la
segunda con el sistema de mampostería
tradicional.
Se recopiló la información en campo en
forma de video de las actividades realizadas en
obra gris para ambos sistemas de mampostería y
se cuantificó el desperdicio de dichas actividades.
Esto con el fin de medir la productividad
de las cuadrillas mediante las metodologías “Five
Minutes Rating” y “Crew Balance”, además de
obtener el rendimiento real de las cuadrillas,
aplicado a las actividades que realizaron y así
desarrollar una programación que determine el
plazo estimado de ejecución de la obra de
acuerdo con el sistema de mampostería utilizado.
Se obtuvo también el presupuesto de las
viviendas, que incluye costo de los materiales
colocados, los desperdicios generados y de la
mano de obra. Se presentan una lista de
problemas de calidad detectados para ambos
sistemas de mampostería.
Se analiza dicha información para
concluir que la diferencia principal entre ambos
sistemas de mampostería se encuentra en la
cantidad y costo de los materiales de desperdicio
generados.
This project is based on comparative analysis of masonry systems Armabloque (modular) and Traditional, focused on cost, time, labor performance and quality. Two housings are evaluated, the first is developed with Modular masonry system and the second one with Traditional masonry system. Information was obtained on site with videos of the activities carried out in gray work for both masonry systems and the waste was quantified. This was made in order to measure crew productivity trough methodologies Five Minutes Rating and Crew Balance, furthermore obtain the crew performance, applied to the made activities and in this way develop a schedule to determine the estimated execution time of the work according to the masonry system used. Also, the housings budget was obtained, including materials cost, waste generated and labor workforce. A list of quality problems detected for both masonry systems is presented. This information is analyzed to conclude that main difference between these systems is on quality and cost of waste material generated.
This project is based on comparative analysis of masonry systems Armabloque (modular) and Traditional, focused on cost, time, labor performance and quality. Two housings are evaluated, the first is developed with Modular masonry system and the second one with Traditional masonry system. Information was obtained on site with videos of the activities carried out in gray work for both masonry systems and the waste was quantified. This was made in order to measure crew productivity trough methodologies Five Minutes Rating and Crew Balance, furthermore obtain the crew performance, applied to the made activities and in this way develop a schedule to determine the estimated execution time of the work according to the masonry system used. Also, the housings budget was obtained, including materials cost, waste generated and labor workforce. A list of quality problems detected for both masonry systems is presented. This information is analyzed to conclude that main difference between these systems is on quality and cost of waste material generated.
Description
Proyecto de Graduación (Licenciatura en Ingeniería en Construcción) Instituto Tecnológico de Costa Rica, Escuela de Ingeniería en Construcción, 2020
Keywords
Productividad, Rendimiento, Sistema de mampostería, Costos, Análisis comparativo, Sistema constructivo, Construcción, Empresas constructoras, Productivity, Performance, Masonry system, Costs, Comparative analysis, Construction system, Construction companies, Research Subject Categories::TECHNOLOGY::Civil engineering and architecture::Building manufacturing engineering